Telupid : Progress work on the proposed St Martin's Pastoral Centre, measuring 70 feet by 100 feet costing some RM800,000 is according to schedule. The concrete floor slab has been completed and the reinforced concrete columns are in place.
Rebar works for the ground beam at the entrance and at the first roof beam are in progress.